| 1876 |
Georgetown's Gas Works is established for the illumination
of the city streets. |
| 1878 |
The Railroad arrives in Georgetown. |
| 1881 |
The Gas works adopts a new more dependable process and new
owners. |
| 1882 |
Thomas Edison's New York City generation plant is in operation. |
| 1886 |
Around December 16, the Electric Light Company in Georgetown
began generating Direct Current (DC) electricity from water
power, the process is known as Hydroelectric generation. |
|
December. 100 street lights are electrically powered in
the town. |
| 1887 |
March. Light switches can be installed in homes,
allowing the user to turn on or off the power to the bulbs
in any room. |
|
Summer. The Gas Company and the Electric Light Company compete
to light the streets. |
|
August. The Gas Company was awarded a contract to light
the streets for three years. |
|
Nikola Tesla invents a electrical generator that produces
alternating current (AC). This discovery now makes the transmission
of electrical power possible over long distances. |
| 1890 |
The Georgetown Selectmen (Town Council) grant a franchise
to construct a new Hydroelectric plant at 4th and Brownell
streets. |
| 1891 |
A new alternating current (AC) plant delivered power to
carbon-arc street lights. |
|
Electrical energy becomes prevalent in mines of the area. |
| 1893 |
April. The assets of the Electric Co. and the Gas Co. were
merged to form the United Light and Power Co. of Clear Creek
County. |
|
August. Street lighting was ordered discontinued because
of the depression caused by the crash of silver prices in
the United States. |
|
Electric service was extended to Silver Plume. |
| 1894 |
September. Electric Light and Power Company closed its gas
works. |
| 1900 |
Georgetown Hydro plant is built at the east end of 6th Street
in Georgetown. |
|
The Alice Chalmers Corliss steam engine was producing power
in October. |
|
Two water wheel generator sets are producing power in November. |
|
Because of the greater head pressure on the south fork of
Clear Creek the electric plant on 4th and Brownell was abandoned. |
| 1901 |
United Light and Power contracted to deliver power to Idaho
Springs. |
|
Increased power production allowed service to other towns
and mines. Electricity allowed marginal mines to remain open. |
|
The 6th street building was completed in April.
|
| 1902 |
United Light and Power buys site allowing the South Clear
Creek dam to be moved up the creek. This adds additional head
of nearly 200 feet to the penstock. The head goes from 480
feet to nearly 670 feet, and the new penstock is 30
in diameter as compared to the old 16 penstock. |
|
July. United Light and Power builds a 20-foot addition to
the north end of the plant. The company had to be granted
the right to move Main Street 20 feet to the north. |
|
A third water wheel generator set was installed. |
|
New brick transformer house completed just to the south
and west of the plant. By late December, the plant is supplying
power to Central City, Black Hawk, and Nevadaville. |
|
The office and coal room were added to the south end of
the building. |
| 1903 |
January. The plant has two generators, 533-horsepower and
400-horsepower. |
|
Dams at Clear and Green Lakes are being raised by about
eight feet each. |
| 1906 |
Two more water-tube boilers added to power new Parson steam
turbine which turns new 500 kW generator. New 90' tall and
5' diameter stack erected by June. Corliss Steam engine still
in service. |
|
Pelton Water Wheel ordered and was installed by May. Replacing
the original water wheel on the 720KW General Electric generator. |
|
February. News of the merger of Green and Clear Lakes Company,
Cascade Electric Company and the United Light and Power Company
to form United Hydro-Electric Company. |
|
April. Work begins on building a 15-foot addition to the
front of the plant to house new switch gear. |
| 1908 |
July. Second Pelton Wheel and new generator installed. |
| 1909 |
A combining gambrel roof was added over the two earlier
gable roofs to better shed the heavy winter snows. |
|
September 24. Flange broke on the 24-inch penstock, flooding
the entire building in knee-deep water. |
|
The Corliss steam engine was removed before WW1. |
| 1911 |
November. United Hydro Electric purchased two new motorcycles
for use by repairmen Hanson and collector Hancock. |
| 1913 |
September. Cement floor poured into office section of plant. |
| 1916 |
July. United Hydro Electric Company sold to Central Colorado
Power Company. |
|
Colorado Power was a conglomerate of several other Colorado
power companies formed in 1913. |
| 1918 |
January. Georgetown Courier reports that the steam
turbine, engine, boiler and big smoke stack of the Hydro Electric
plant, which has been standing idle for several years, is
being taken out and will probably be shipped to Salida for
use at the Colorado Power Company's plant there. |
|
January. Charles Melvin, contract worker at the plant, is
electrocuted on the roof. |
|
March. Retired equipment from steam era is loaded on cars
for shipment out. |
|
The 90' smoke stack was removed and shipped to another location. |
| 1919 |
June. Company purchased Dodge truck to replace the team
of animals used for 18 yr. |
| 1920 |
May. The planing mill erected in the 1870s is torn down
by the power company. |
| 1924 |
Colorado Power Company was renamed as Public Service of
Colorado. |
| 1939 |
Water wheel no. 2 modified for greater capacity; water line
and needle valve enlarged. |
|
The railroad rails were removed from Georgetown. |
| 1941 |
The 1902 penstock was replaced and rerouted to the east
side of the building. The high combining roof was removed.
The Engine room and Machine shop areas roof turned 90 degrees
and reinforced with steel to the present configuration.
|